PHOTOVOLTAIC SYSTEM 3 MW – CORATO

Description

Ground photovoltaic system, called “Pedale” for the electricity generation with an output of 3 MW. Single authorization legislative decree n.387/2003. The system was authorized and realized according to the choice of the energy service, networks and material infrastructures’ manager for the development of Region Of Apulia of 16th July 2010, n. 179. In collaboration with General Contractor: URBE TECHNO srl e ZARAGOZA —Spagna

Description

DATE
2011
LOCATION
Corato (BA)
CUSTOMER
PEDALE srl

FOCUS

  • Preliminary design;
  • Final Design (Legislative Decree n. 163/2006 and Presidential Decree n.554/99);
  • Coordination of Authorisation procedures;
  • Works management;
  • Security coordination at the design stage and during implementation;
  • Relationships with different corporations (Enel, GSE, Customs Agency) for any authorization.